QuantProblem Solving

Free GMAT Problem Solving Practice Question

PrepLattice is an independent test-preparation service and is not affiliated with or endorsed by GMAC, the organization that administers the GMAT. GMAT and GMAT Focus are trademarks of GMAC, used here only to name the exam this question is designed to prepare you for.

Loom P, working alone, takes 5 hours longer than Loom Q takes to weave one bolt of cloth, and the two looms running together weave one bolt in 6 hours. On a certain day, Loom P weaves a bolt alone for the first 5 hours, after which Loom Q joins it and the two finish the bolt together. How many hours in total does it take to weave that bolt?

Five fresh questions every day, your progress tracked, every miss explained. Free with an account.

Answer & Explanation

Correct answer

E

If the two looms together weave one bolt in 6 hours, their combined rate is 1/6 of a bolt per hour.

Let Loom Q take t hours alone, so Loom P takes t + 5 hours alone. Rates add: 1/(t + 5) + 1/t = 1/6. Multiply through by 6t(t + 5): 6t + 6(t + 5) = t(t + 5), so 12t + 30 = t² + 5t, giving t² − 7t − 30 = 0, or (t − 10)(t + 3) = 0. The root t = −3 is rejected, so t = 10. Loom Q takes 10 hours alone (rate 1/10) and Loom P takes 15 hours alone (rate 1/15).

Now handle the staggered start. Loom P runs alone for the first 5 hours at rate 1/15, weaving 5 × (1/15) = 1/3 of the bolt. The remaining work is 1 − 1/3 = 2/3. Once Loom Q joins, the two work at 1/6 per hour, so the remaining 2/3 takes (2/3) ÷ (1/6) = 4 hours. Total time is 5 + 4 = 9 hours. The answer is E.

The wrong choices each mishandle one step. 4 (A) is only the finishing phase, reported without adding the 5-hour head start. 6 (B) reports the plain together-time and ignores the head start. 7 (C) treats the remaining work as 1/3 instead of 2/3, confusing the fraction done with the fraction left. 8 (D) swaps which loom runs solo first, using the faster loom for the opening 5 hours. Plugging answer choices back in is no shortcut, since checking any total still requires solving the quadratic and redoing the staggered-completion logic.

As an independent check, confirm the solo rates against the given joint time: 1/15 + 1/10 = 2/30 + 3/30 = 5/30 = 1/6, which matches the stated 6-hour together-time, so the rates 1/15 and 1/10 are correct. Then verify by the work done rather than by re-deriving the time: in the first 5 hours Loom P lays down 1/3 of the bolt, and over the final 4 hours the pair lay down 4 × (1/6) = 2/3; the two pieces sum to 1/3 + 2/3 = 1 whole bolt, so the 9-hour total is consistent.